CPM Enterprise

CPM Enterprise

Carolina Projects Management Enterprise

Commercial & Residential

Norris Park Office Building

Location: Apex, NC.

Brief: Construction of Foundation – Slab On Grade – Tilt Up Panels – Slab On Metal Deck Structural Steel – exterior pavement – dumpster.

Scope of Work: Drawings Review – Site Management – Cost Estimation – Cost Control – Schedule Control – Baseline Schedule – Schedule Updates.

Low Country

Location: Charleston, SC.

Brief: Constructing a 52,000 square foot, state-of-the-art facility. The manufacturing space is divided into (4) separate divisions; cabinetry, millwork, finishing, and a climate controlled shipping department.

Scope of Work: Drawings Review – Ordering Materials -Estimate Change Order – Cost Control – Schedule control – Lifting sequence and crane path

Carolina Commercial Parkway

Location: Charleston, SC.

Brief: Construction of Foundation – Slab On Grade – Tilt Up Panels – Slab On Metal Deck Structural Steel.

Scope of Work: Checking drawings – Ordering materials – Estimate change order – Cost Control – Schedule Control – Lifting sequence – crane path.

Cross pointe Church

Location: Cary, NC.

Brief: They needed to extend the project by adding 92,363 square foot to the existing structure. The method of construction used was Tilt Up construction.

Scope of Work: Drawings Revision – Simulate the lifting sequence using Revit – Preliminary Schedule – Baseline Schedule – Monthly Schedule updates – Schedule Control – Cost Estimation – Cost Control – Progress field meetings to check safety, quality – solve onsite issues and attend preconstruction and pre-pour meetings.

Bishop Grant Lot 9

Location: Wake Forest, NC.

Awarded Company: YZ Homes

Brief: Constructing a house from the permit phase till the finishing and close out.

Scope of Work: Preliminary Schedule – Baseline Schedule – bi-weekly Schedule updates – Schedule Control – Cost Estimation – Cost Control –

Kabab Skewer Restaurant

Location: Cary, NC.

Brief: Renovation of the whole restaurant.

Scope of Work: Remodeling – scheduling.

Cary MOB

Location: Cary, NC.

Awarded Company: Healthcare trust of America Inc.

Brief: Construction of Three stories Medical offices building.

Building size equals to 56,865 square foot.

Scope of Work: Checking Drawings- Ordering Materials – Estimate Change Order – Cost Control – Schedule Control.

Belle Hall Office Building

Location: Mount Pleasant, SC.

Brief: Construction of Foundation – Slab On Grade – Tilt Up Panels – Slab On Metal Deck Structural Steel.

Scope of Work: Checking drawings – Ordering materials – Estimate change order – Cost Control – Schedule Control – Lifting sequence – crane path.

Perimeter Park Office Building

Location: Morrisville, NC.

Brief: Construction of Foundation – Slab On Grade – Tilt Up Panels – Slab On Metal Deck Structural Steel for Office Building:

1st floor= 33,004 2nd floor= 33,516

3rd floor= 33,516 Total= 100,036 sf

Scope of Work: Cost Estimation – Cost Control – Preliminary Schedule – Baseline Schedule – Schedule Updates.

Humie Olive Subdivision

Location: Apex, NC.

Awarded Company: YZ Homes.

Brief: Constructing a subdivision including 8 Town Houses

Scope of Work: Preliminary Schedule – Baseline Schedule – bi-weekly Schedule updates – Schedule Control – Cost Estimation – Cost Control for the whole project including the subdivision and the houses.

MYCC Community Center

Location: Raleigh, NC.

Awarded Company: MYCC.

Brief: Constructing of a Community Center that consists of 20,000 sf building with Gym, classes, event rooms, and indoor basketball. On the outside it has a soccer field, 1 volleyball fields, another basketball field, parking lots and green areas.

Scope of Work: Preliminary Schedule – Baseline Schedule – bi-weekly updates – Schedule Control – Cost Estimation – Cost Control –

Gateway

Location: Mount Pleasant, SC

Brief: Construction of Foundation – Slab On Grade – Tilt Up Panels – Slab On Metal Deck Structural Steel – exterior pavement and dumpster

Scope of Work: Drawings Review – Ordering Materials -Estimate Change Order – Cost Control – Schedule control – Lifting sequence and crane path

Oasis Subdivision

Location: Raleigh, NC.

Awarded Company: YZ Homes.

Brief: Constructing an 11 acre subdivision including around 33 duplexes and three story houses.

Scope of Work: Preliminary Schedule – Baseline Schedule – bi-weekly Schedule updates – Schedule Control – Cost Estimation – Cost Control for the whole project including the subdivision and the houses.